Programme · Nov 2025 to present

Regional decarbonisation pilot programme

Responsible for the analysis across all pilots

Five pilot companies in a regional decarbonisation programme run with a public partner organisation. Each one took its own initiative from the first data request to a go or no-go decision at board level.

pilot companies in the portfolio

full fleet electrification studies led from start to finish

tonnes CO2 per year in the largest single baseline

cubic metres per year, first measured water baseline

The brief

The programme brings together a regional climate partner and local companies that want to put a decarbonisation initiative through a real feasibility process. There were five companies in the portfolio. I did the analysis: whatever each company needed measured, modelled and checked, I handled from start to finish.

The five companies were in different sectors and at different stages, so each pilot ran differently. Two were heavy transport companies, and those became full electrification studies. One had a process-water problem in surface treatment. One was about compressed air and condition monitoring in precision manufacturing. One never got past scoping.

The portfolio

The five companies.

Described by sector only. Each one ran on its own timeline.

Feed and heavy transport

Fleet electrification, four tractor units

The study went through seven numbered versions, a forensic audit and an independent validation pass. The chief executive was briefed and approved the concept, and asked for real-world testing before committing any capital.

Waste and recycling transport

Two-truck electrification plus rooftop solar

Management briefing delivered and a combined energy-transition case built. The programme used it as its public reference story for the quarter.

Cold forging and surface treatment

Counter-current cascade rinse and vacuum evaporator

A buildable design fixed against the existing tank layout, projecting a 90 to 95 percent cut in wastewater. Management agreed in principle to a 2030 timeline, driven by new EU best-available-technique rules that are on the way.

CNC manufacturing

Compressed air optimisation and condition monitoring

Two initiatives taken to the point where management can decide. The first saves roughly DKK 278k a year against DKK 30k net capital, so it pays back within weeks. It needed no new equipment, only a leak audit and a pressure reset.

Agriculture

Ventilation and energy efficiency

Scoped but dormant. No data, meetings or analysis on record. I reported it as dormant, kept it out of the pipeline numbers, and suggested a partner introduction to get it going again.

Deliverables

What I delivered.

Portfolio briefing for the programme partner

One document with all five pilots side by side: stage, likelihood, economics and what we needed from the partner for each one. It also said plainly that the programme milestone had been missed, and gave a new one.

Two complete fleet electrification feasibility studies

Each one covers duty-cycle analysis from measured telematics, a ten-year total cost of ownership model, charger sizing based on metered depot load, and a recommendation to convert in phases.

Process and energy initiative cases

Measured baselines and investment cases for the water, compressed air and condition monitoring initiatives. Each one shows capital cost, annual saving, payback and the CO2 effect.

Depot charging capacity analyses

Three and a half years of metered load data, used to answer a simple question: how much charging can each site handle tonight without grid work, and what would an upgrade add?

Actions

What I did.

  • Ran each pilot from the first data request to the recommendation presented to the company's management.
  • Pulled together operational data from systems that were never built to share data: telematics, ERP cost accounting, transport management records, fuel cards and the national vehicle registry.
  • Built the financial models for every initiative, and wrote the discount rate, the time horizon and how subsidies were treated on the front of each document.
  • Graded every dataset for reliability and marked every figure as factual, calculated or estimated, so if someone questioned a number it could be traced back in one step.
  • Told the partner when it was clear the original milestone would be missed, and gave a new target and the reason for the delay.

Problems and solutions

What went wrong, and how I handled it.

Every project hits problems along the way. These are the ones that mattered here.

Problem

The programme's original goal was two approved initiatives by the end of May. That date passed with the analysis done but no formal sign-offs.

Solution

I reported it as it was. The briefing said the milestone had passed and that the analysis was finished; what held things up was management taking longer to decide. I proposed a new target of two to three approvals by the following quarter, and named the specific decision each pilot was waiting on.

Problem

One of the five pilots had produced nothing: no meetings, no data, no analysis.

Solution

I listed it in the portfolio table as dormant, with its likelihood marked to match, and asked the partner for an introduction to restart it. Showing it as active would have hurt our credibility the first time anyone asked about it.

Problem

Five companies in five sectors meant five different analysis problems, with no shared method to start from.

Solution

Each case needed its own model. What I could reuse was the way of working: measure a baseline first, use conservative assumptions, grade the data for reliability, and end with one recommendation. The water and compressed air cases share no calculations with the fleet studies, but I graded and checked them the same way.

Outcome

The analysis is now done across the portfolio, so it is no longer what holds things up. Four of the five pilots have a case that management can act on, and the fifth is clearly marked as dormant. The two fleet studies became the base for the platform's first licensable product.

Skills and tools used

Total cost of ownership modellingData reconciliationReliability gradingStakeholder reportingExcel financial modelsPython